A Subcontractor Agreement in Israel: The Clauses That Decide When the Client Does Not Pay or the Work Goes Wrong

קו אור יחיד מצייר בלילה שלד של בניין בבנייה ושלוש חוליות של שרשרת, להמחשת הסכם קבלנות משנה וחלוקת הסיכונים בין מזמין, קבלן ראשי וקבלן משנה

By Adv. David Bodenheim, Partner, Head of Litigation | Published: November 2026

A subcontractor agreement is a separate contract from the contract between the client and the main contractor. Between the subcontractor and the client there is, as a rule, no contractual privity, and so each party depends on what was written in its own agreement: when payment is made, what happens when the client does not pay, who approves changes, who bears defects and delays, and where a dispute is heard. The clause that produces most disputes is the “back-to-back” clause, and the Supreme Court already held, in a decision of 2010, that its mere existence does not cancel the debt to the subcontractor for work that was performed.

In a project that runs smoothly, the agreement is hardly ever opened. It is tested when the client delays an invoice, when a defect is discovered after handover, or when one of the parties in the chain runs into difficulties. This guide goes through the clauses where the outcome is decided, from the point of view of both the main contractor and the subcontractor.

Key points

  • Two contracts, two relationships. What was not copied from the main contract into the subcontract does not bind the subcontractor automatically.
  • A “back-to-back” clause is intended, as a rule, to protect the main contractor against non-payment that stems from the subcontractor, and not to shift the entire risk to him.
  • Whoever wants one obligation to be conditional on another must write so expressly. The courts are not quick to read in a condition that was not written.
  • Changes and quantities are approved in writing and in real time. Without that, the final accounting becomes an evidentiary dispute.
  • A defect must be notified, and an opportunity to repair must be given. This is what the Contract for Services Law provides, and it applies between a main contractor and a subcontractor as well.
  • The dispute resolution mechanism in the subcontract needs to match the one in the main contract, otherwise the main contractor will litigate in two arenas.

Two contracts, not one: why does it matter?

The Contract for Services Law defines a contract for services as a contract for the doing of work or the giving of a service for remuneration, where the contractor is not the employee of the client. The subcontract is also such a contract, and in it the main contractor is “the client”. As Prof. Eyal Zamir explains in his study of subcontracting, the starting point is that there are two separate engagements, and that there is no contractual privity between the client and the subcontractors. The meaning is twofold: the main contractor remains liable to the client for everything the subcontractor performed, and the subcontractor claims his remuneration from the main contractor, not from the client.

Therefore, Zamir writes, it is essential to incorporate into the subcontract what the main contract provides regarding the work: specifications, timetables, quality requirements and the sanctions for breaching them. The provisions of the Contract for Services Law apply only where no other intention is implied by the agreement, so most of the rules are for the parties to shape.

“Back-to-back”: does the subcontractor wait until the client pays?

A “back-to-back” clause provides, in various wordings, that the subcontractor will receive the consideration only after the main contractor has received it from the client. The question is what happens when the client does not pay at all, for example because it collapsed or because it is in dispute with the main contractor.

In a decision of 2010 (the Tzevet Karka case), Supreme Court Justice Yoram Danziger rejected the argument that the mere existence of the clause cancels the debt to the subcontractor. He held that its purpose, as a rule, is to prevent a situation in which the contractor is forced to pay the subcontractor for work that was not approved and not paid for because of factors connected with the subcontractor, such as partial or defective work. In that case the client went into liquidation, and it was held that this does not cancel the main contractor’s liability to the subcontractor who performed the work.

Precision is needed here: this is a decision of a single justice on an application for leave to appeal, not a comprehensive judgment. In 2018 Justice Anat Baron noted, in a decision in the case of Dori Construction v. Netivim Darom, that the proper interpretation of back-to-back clauses is a weighty question that has not yet been discussed at length in the Supreme Court, and that there are conflicting rulings in the trial courts. In that matter the Tel Aviv District Court held that the clause was not intended to place the entire risk on the subcontractor, that in order to be released from payment the main contractor must show a link between the client’s non-payment and an act or omission of the subcontractor, and that a main contractor, who stands in the middle, owes the subcontractor a heightened duty of good faith.

The practical conclusion for both sides: the wording decides. A clause that governs only the timing of payment is different from a clause that expressly shifts the risk of the client’s insolvency, and even the latter can be relied on only in good faith.

The “back-to-back” clause

What each side needs to write

The same clause, two interests. The more explicit the wording, the smaller the room for dispute.

The main contractor

An express condition, not just a date

If the intention is that payment is conditional on receiving the money from the client, write so in clear words.

A link to the client’s approval

Payment only for quantities and works that the client or the supervisor approved.

Transparency and documentation

Keep the subcontractor updated on the state of the accounts with the client, and act to collect them.

The subcontractor

A final date for payment

A date on which the consideration is paid in any event, even if the client is late.

Only what depends on him

Payment is withheld only when the client did not pay because of the subcontractor’s own work.

A right to information

Copies of accounts and approvals, and an undertaking by the main contractor to act to collect.

RememberAccording to the Supreme Court, the clause does not by itself cancel the debt for work that was performed (LCA 3458/10).

A condition or an independent undertaking? It has to be written expressly

In August 2024 the Supreme Court considered a “back-to-back” subcontractor agreement in a large infrastructure project (the Adeltech case). One of the questions was whether a payment undertaking included in the agreement was conditional on the performance of another obligation, a duty to cooperate, which was written immediately after it. The majority held that it was not. The court restated the rule that whether obligations are independent, concurrent or conditional is a question of interpretation, whose starting point is the language of the contract as a whole, and that extra caution is called for when the language does not support an interpretation of a conditional obligation. Whoever wants to make his liability conditional on the performance of an obligation by the other party must say so expressly. The fact that in other clauses of the same agreement the parties knew how to write “conditional on” worked against the party who argued for a condition that was not written.

The lesson goes beyond payment. Guarantees, indemnity, handover approvals and the release of retained sums also need to be written so that it is clear whether they are a condition for another obligation or an obligation that stands on its own.

Changes, quantities and approvals: where does the accounting fail?

In most of the disputes that reach us, the disagreement is not about the unit price but about what was actually performed: additional works ordered orally, quantities measured differently, and a final account that no one approved. A good agreement provides who is authorized to order a change, in what form, and what happens when the work was performed before written approval was received. It also provides within what time the main contractor examines an interim account, and what the status is of an account that received no response.

This is also the point at which the two contracts meet. If the client pays the main contractor only for quantities approved by its supervisor, the subcontract needs to provide who presents the quantities to the supervisor, and whether the subcontractor has a right to be present at the measurement.

Defects, the warranty period and delays: who bears what?

The Contract for Services Law sets a clear order. The client must notify the contractor of a defect within a reasonable time after discovering it, and if the defect can be repaired, give him a proper opportunity to repair it. A client who did not do so may not rely on the defect, unless the contractor knew of it. Only if the contractor did not repair within a reasonable time may the client repair it himself and demand his reasonable expenses, or deduct from the remuneration. In the relationship between the main contractor and the subcontractor, this means that a main contractor who received a repair demand from the client needs to pass it on at once to the subcontractor and allow him to repair, and not repair through someone else and set off.

With delays the problem is different. A delay by one subcontractor may hold up the entire project and expose the main contractor to damages toward the client. Zamir points out that under the Remedies Law the main contractor is entitled to compensation only for damage that the subcontractor could have foreseen at the time the contract was made, and it is therefore advisable to bring to his knowledge in advance the possible consequences of a breach, including the damages in the main contract. On the other side, a subcontractor needs to make sure that he is liable only for a delay caused by him, and that there is a mechanism for extending the timetable when the delay stems from others.

The clauseWhat should be writtenWhat happens when it is missing or vague
Date of payment and “back-to-back”Whether it is a date or a condition, and what the final date for payment isThe court will interpret, and usually will not release the main contractor from paying for work that was performed
Scope of work and incorporation of the main contractWhich documents of the main contract are binding, and what prevails in a conflictThe client’s requirements do not bind the subcontractor automatically
Changes and quantitiesWho approves, in what form, and within what time an account is examinedAn evidentiary dispute over what was ordered and what was performed
Defects and warranty periodHow notice is given, time for repair, the guarantee and the conditions for its returnThe rules of the Contract for Services Law apply: notice and a proper opportunity to repair
Delays and liquidated damagesMilestones, grounds for extension, and a link to the damages in the main contractCompensation only for damage that was foreseeable when the agreement was made
Termination, removal from site and set-offGrounds, notice, accounting for what was performed, and the scope of the right of set-offAn unlawful cancellation may turn the cancelling party into the party in breach
Dispute resolutionA court or arbitration that is coordinated with the main contractDouble litigation and decisions that may contradict each other

Dispute resolution: how not to be left in the middle

The Netivim Darom affair illustrates the risk. A subcontractor sued the main contractor in the District Court for works whose consideration had not been paid. The main contractor, which was in dispute with the client, sent the client a third-party notice, but the main contract provided for arbitration abroad, and the notice was stayed. In July 2015 the Supreme Court, per Justice Noam Sohlberg, also set aside the joinder of the client as a defendant, and stressed that these are two different relationships, which arise from different agreements, with separate claims and facts. The result: the main contractor defended itself in court against the subcontractor, and at the same time conducted an arbitration against the client over the same works.

This is solved at the drafting stage. If the main contract has an arbitration clause, it is worth considering a matching clause in the subcontract, or a mechanism that allows overlapping disputes to be heard together.

Six things to check before signing

  1. Read the main contract. A subcontractor who undertakes “all the provisions of the main contract” needs to receive it, at least in the parts that concern his work.
  2. Define the payment. Dates, milestones, the sum retained from each account and when it is released, and what “back-to-back” means if it is included.
  3. Set a change mechanism. A form, an authorized signatory and a unit price for additional works.
  4. Coordinate liability and insurance. The warranty and liability period, the guarantees, the insurance policies, and who is responsible for safety on site.
  5. Regulate termination. When removal from site is permitted, what is paid for what was performed, and what happens to equipment and materials left on site.
  6. Coordinate dispute resolution. The same forum or the same mechanism in both agreements, as far as possible.

If you are based abroad

Foreign contractors and suppliers working on projects in Israel usually sign a subcontract governed by Israeli law. You do not need to be in Israel to have it reviewed or enforced: our office can review the agreement against the main contract, conduct the correspondence and the proceedings in Israel, and act under a power of attorney signed before an Israeli consul, or before a local notary with an apostille.

Frequently asked questions

The client did not pay the main contractor. Can the subcontractor sue the client directly?

As a rule not on the basis of the contract, because there is no contractual privity between them. A direct claim is possible only when there is a separate basis, for example an undertaking that the client gave the subcontractor directly, or an assignment of the main contractor’s right to payment. A subcontractor who is concerned about the stability of the main contractor therefore needs to arrange such a security in advance.

My agreement says “back-to-back”. Do I have to wait until the client pays?

It depends on the wording and on the reason for the non-payment. The Supreme Court held that the clause does not by itself cancel the debt for work that was performed, and that its purpose is usually to protect the main contractor when the non-payment stems from the subcontractor. There are different approaches in the trial courts, and so each agreement is examined according to its language and circumstances.

The main contractor repaired a defect through someone else and set it off from my account. Is he allowed to?

Under the Contract for Services Law, before self-repair the contractor must be notified of the defect and given a proper opportunity to repair, unless the repair is urgent. If no such opportunity was given and the agreement does not provide otherwise, there is a basis for disputing the set-off.

Additional works were ordered from me orally. Will I be paid for them?

An order can be proved even without a signed document, but the burden is on you, and many agreements require written approval as a condition for payment. Send a written confirmation on the day of the order, even by message, and document the performance.

May a main contractor pass all the work on to a subcontractor?

It depends on the main contract. Many contracts make the engagement of subcontractors conditional on the client’s approval, and there are works that by their nature are intended for personal performance. In any event, passing on the performance does not release the main contractor from his liability to the client.

About to sign a subcontractor agreement, or in the middle of a dispute over an account?

Our firm accompanies main contractors, subcontractors and developers in drafting agreements, in final accounting and in performance disputes, in the courts and in arbitration. Accompaniment at the drafting stage usually saves most of the disputes. We represent clients throughout Israel and abroad, mostly by phone and video.

For an initial conversation: +972-2-509-0170
Adv. David Bodenheim, Partner, Head of Litigation at Bodenheim Gabriel & Co., represents developers, contractors and property owners in construction and real estate disputes in all courts. Our litigation practice. Bodenheim Gabriel & Co., 214 Jaffa Street, Jerusalem.

This article is intended for general information only and does not constitute legal advice or a substitute for it. Every case is examined on its own circumstances. Last updated: November 2026.

Main sources

  • Contract for Services Law, 5734-1974, Sections 1 to 4 and 8
  • Contracts (General Part) Law, 5733-1973, Section 43(a); Contracts (Remedies for Breach of Contract) Law, 5731-1970, Section 10
  • LCA 3458/10 Tzevet Karka v. HaKodchim Shabbat Ltd. (Supreme Court, decision of Justice Danziger, September 5, 2010)
  • CA 3314/18 A. Dori Construction Ltd. v. Netivim Darom Ltd. (Supreme Court, decision of Justice Baron on an application for a stay of execution, July 11, 2018), including the description of the judgment of the Tel Aviv District Court in Civil Case 29431-09-13
  • LCA 2228/15 G.T.S. Power Solutions Limited v. Netivim Darom Ltd. (Supreme Court, July 9, 2015)
  • CA 8316/21 Adeltech Holdings (2006) Ltd. v. Amos Luzon Development and Energy Group Ltd. (Supreme Court, August 14, 2024)
  • Eyal Zamir, “Subcontracting: The Relations Between Client, Contractor and Subcontractor”, Mechkarei Mishpat (1994); Eyal Zamir, Contract for Services Law, 5734-1974 (1994)