By Adv. David Bodenheim, Partner, Head of Litigation | Published: November 2026
The house committee (Va’ad Bayit) of a condominium building may sue the developer, on behalf of all the apartment owners, for defects in the common property, and may demand an order to repair them or compensation in the amount of the cost of repair. It may not, by force of the law alone, claim the personal damage of the residents, such as loss of value of the apartments or distress. Those are claimed by each apartment owner personally, or the owner authorizes the house committee to do so by an express authorization. The Supreme Court clarified this distinction in December 2022, and it has implications for the way the claim is planned.
Stone cladding that falls off, failed waterproofing on the roof or in the car park, a lift that is out of service again and again, a main pipe that leaks: these are defects that do not “belong” to a particular apartment, and so no resident hurries to deal with them alone. This guide explains who may claim what, how much is received when only some of the residents join, and what needs to be done before a claim is filed.
Each of the apartment owners. The Supreme Court held in the Acrylit case (2012) that the seller’s obligations under the Sale (Apartments) Law relate not only to the apartment itself but also to the common property, and that a non-conformity in the common property is like a non-conformity in the apartment. The seller must provide each buyer with an undivided proportionate share in common property that is in proper condition. The cause of action is contractual, between the seller and the buyer, and the law also grants it to a subsequent purchaser, that is, to a person who bought the apartment from the original buyer.
The common property is defined in the Land Law: all parts of the building other than the parts registered as apartments, including the land, the roofs, the external walls, the foundation, the stairwells, the lifts, the shelters and installations intended to serve all or most of the apartment owners.
Section 69 of the Land Law provides that the house committee serves as the authorized representative of all the apartment owners in any matter concerning the proper maintenance and management of the condominium building, and that in these matters it is entitled to enter into contracts and to be a party to any legal proceeding on behalf of all the apartment owners. The power is broad, but it is confined to what the section lists.
In a judgment of December 2022 (LCA 7602/22), which concerned a residential building in Jerusalem whose stone cladding was found to be defective, Supreme Court Justice Ruth Ronen summarized the law as follows:
In that case this finding had great practical significance. The developer argued that an earlier claim, to which the house committee had been joined for the purpose of repairing the cladding, barred the residents from now claiming loss of value. The court rejected the argument: since the house committee had not been authorized to claim the personal damage, no res judicata arose in respect of it.
Defects in the common property
Who claims what
Under Section 69 of the Land Law and the case law of the Supreme Court.
The house committee, on behalf of all the owners
An order to repair the defect
Requiring the developer to repair the cladding, the waterproofing, the lift or the shared piping himself.
Compensation in the amount of the cost of repair
Money intended for carrying out the repair of the common property.
Managing the proceeding and the experts
One engineering opinion for the building, one lawyer, one fund.
Each owner, personally or by express authorization
Loss of value of the apartment
Personal damage that is proved for each apartment separately.
Distress
A personal entitlement by its nature, dependent on each resident’s circumstances.
Defects in the apartment itself
Damp, flooring, aluminium work and everything inside the apartment.
The apartment owners, all or some of them, may authorize the house committee to act as their agent also in matters outside Section 69. The Supreme Court held so as early as 1981, in the Kidmat Lod case, as mentioned in the 2022 judgment. But the authorization has to meet the requirements of the law of agency, and in that judgment it did not meet them. Four rules can be derived from the reasoning:
This is the question on which many claims stumble. Under the Hashai rule, which the Supreme Court restated in the Acrylit case, when some of the residents claim monetary compensation for defects in the common property, each resident who proved his claim is compensated according to his proportionate share in the common property. The meaning: if the owners of half of the apartments sued, only about half of the cost of repair will be awarded, and the repair will not be carried out.
In the Acrylit case a way was found to reduce the difficulty. The residents there had already replaced the cladding at their own expense, and the court held that when the compensation is intended to finance the repair itself, it is equivalent to a remedy of specific performance, and the seller can be charged with the full cost of repair even when only some of the buyers sue. The shares of residents who knew of the defect when they bought, and of residents who took part in the cost of repair but did not sue, were deducted from the sum. Compensation for distress was awarded only to those who bought directly from the defendants, because this is a personal entitlement.
The same judgment clarified that joining the house committee as a claimant is useful in order to ensure that the money is used for the repair, but it does not add to the buyers’ cause of action and is not a substitute for joining the apartment owners themselves. The practical conclusion: the more apartment owners join as claimants, alongside the house committee, the stronger the claim.
The Sale (Apartments) Law makes reliance on a non-conformity conditional on two steps. The first is notice: a defect that could have been discovered at handover must be notified to the seller within one year, and a defect that could not have been discovered on a reasonable inspection, within a reasonable time after it was discovered. The second is a proper opportunity to repair, with the seller required to repair within a reasonable time. If the defect recurred after it was repaired, within two years of the notice, or the repair is urgent and the seller did not carry it out within a reasonable time, the buyer may repair it himself and the seller will bear the expenses.
| The defect in the common property | Warranty period under the Schedule to the Law |
|---|---|
| Detachment, peeling or crumbling of external cladding | Seven years |
| Cracks more than 1.5 mm wide in non-load-bearing elements | Five years |
| Failure of the waterproofing of the structure, including roofs, walls and underground spaces | Four years |
| Failure of piping systems, including water, sewage and gutters | Four years |
| A defect in the landscaping of the yard, in parking spaces and in paths; failure of machinery and boilers | Three years |
| Any other non-conformity that is not fundamental | One year |
During the warranty period, it is the seller who has to prove that the defect was caused by the buyer. It is followed by a liability period of three years, in which the buyer has to prove that the source of the defect lies in the design, the work or the materials. For a fundamental non-conformity, in the load-bearing parts of the building, a warranty period of 20 years was set. The periods are counted from the date the apartment was placed at the buyer’s disposal, and so in a building that was occupied in stages it is advisable to document the handover dates.
Apartment owners who live abroad can join a claim over defects in their building without coming to Israel. The personal authorization or power of attorney is signed before an Israeli consul, or before a local notary with an apostille, and our office handles the proceedings in Israel and keeps you updated.
For the repair of defects in the common property or for the cost of repair, yes: this is a power the law gives it as the authorized representative of all the apartment owners. Nevertheless, the house committee is subject to the resolutions of the general meeting, and so it is right to adopt an orderly resolution on the proceeding and its financing. For personal damage, an authorization is needed from each apartment owner who wants a claim to be brought in his name.
Yes. The Sale (Apartments) Law grants the rights to a subsequent purchaser as well. The main reservation is knowledge: a person who knew of the defect when he bought the apartment cannot claim its repair, and his share may be deducted from the compensation.
The law requires that the developer be given a proper opportunity to repair. If he repaired properly, there is usually no ground for compensation for the cost of repair. If the repair failed and the defect recurred, or the developer does not repair within a reasonable time, the way is open to self-repair at his expense or to a monetary claim.
Not necessarily. After the warranty period there is a liability period of three years, and for a fundamental defect the periods are far longer. What changes is the burden of proof. Beyond that, the general law of limitation applies, and so it is not advisable to wait.
Money awarded as the cost of repairing the common property is intended for the repair. It is advisable to decide in advance, by a resolution of the general meeting, that it will be deposited in the building’s account and used only for that purpose, and what will be done with any balance.
Our firm represents house committees and apartment owners in construction defect claims against contractors and developers: from the notice of defects and the expert opinion, through the authorizations and the general meeting, to a judgment or a settlement. Correct planning of who the claimants are and which remedies are sought determines the outcome. We represent clients throughout Israel and abroad, mostly by phone and video.