The Warranty Guarantee in Israeli Construction Contracts: When the Contractor Gets It Back, and When the Client May Call It

קו אור יחיד מצייר בבוקר בניין מגורים חדש ולידו מסמך ערבות עם חותמת ושעון חול קטן, על רקע אתר בנייה ירושלמי מואר, להמחשת ערבות בדק שמוחזקת עד תום תקופת הבדק

By Adv. David Bodenheim, Partner, Head of Litigation | Published: November 2026

The warranty guarantee (Arvut Bedek) returns to the contractor at the end of the period set in the contract, if it was not called earlier. Until then it is security in the client’s hands, and if it is an autonomous bank guarantee the client may demand payment under it without proving to the bank that the contractor breached the contract, and may also put a choice to the contractor: extend it or it will be called. And what was collected beyond what was due to the client? That can be claimed back, but only after the call.

In the disputes our office conducts between developers and performing contractors, the disagreement over the warranty guarantee usually arrives years after the building was handed over, when the people who signed the contract have already changed. What decides the matter then is what was written in the contract and in the guarantee document, and what was documented during the warranty period. This guide explains the rules from both sides.

Key points

  • A warranty guarantee secures the contractor’s obligation to repair defects discovered after handover. Its period is set in the contract, not in the law.
  • Developers usually tie it to the warranty periods that they themselves owe the apartment buyers under the Sale (Apartments) Law.
  • Before repairing at the contractor’s expense: notice of the defect and a proper opportunity to repair.
  • An “extend or pay” demand, sent while the guarantee is still in force, is legitimate.
  • The court will not stop a call because of a contractual dispute. The contractor’s remedy is a restitution claim.
  • The expiry of the guarantee does not end the liability for defects. It only removes the security.

What is a warranty guarantee, and for how long is it given?

In construction contracts it is customary for the contractor to deposit a performance guarantee with the client for the period of the works, and for it to be replaced on completion of the building by a warranty guarantee, also called a quality guarantee. Its purpose is to ensure that the contractor repairs defects discovered after handover, and that if he does not, the client has something to collect from. It is usually an autonomous bank guarantee, renewed from time to time.

The law does not provide how long the warranty guarantee will be in force or what its amount is. These are matters for the contract. But there is a reason why the periods are long: a developer who sells apartments owes the buyers liability under the Sale (Apartments) Law. The warranty periods in the Schedule to the Law range from one to seven years, according to the type of defect, and they are counted from the date the apartment was placed at the buyer’s disposal. They are followed by a liability period of a further three years. The developer wants the security he holds against the contractor to cover, as far as possible, the period in which he himself is exposed.

This was the position in a case decided by the Supreme Court in February 2010 (CA 616/07). The contract between the developer and the contractor provided that the guarantee would be in force until the end of the warranty period “from the date of handover of all the apartments”, that the term “warranty period” would be interpreted according to the Sale (Apartments) Law, and that at the end of six years from the handover of all the apartments the guarantee or its balance would be returned to the contractor, “to the extent that it was not called earlier”. Note the starting point: the handover of all the apartments, not the handover of the first apartment.

What must the client do before repairing at the contractor’s expense?

Alongside the contract, the Contract for Services Law applies. Under Section 3, a client who discovered a defect must notify the contractor of it within a reasonable time after he discovered it or should have discovered it, and if the defect can be repaired, give the contractor a proper opportunity to repair it. A client who did not do so is not entitled to rely on the defect, unless the contractor knew of it. Under Section 4, if the contractor did not repair within a reasonable time, the client may repair it himself and demand his reasonable expenses, or deduct from the remuneration the amount by which the value of the work was reduced. A defect whose repair is urgent can be repaired without waiting.

The warranty guarantee is the way the client collects these expenses without a lawsuit. Documentation is therefore important to both sides: to the client, in order to show that he gave notice and an opportunity; and to the contractor, in order to show that he repaired or that he was not given the chance.

Warranty guarantee

From the contract to the return

Five stations at which it is determined whether the guarantee will return to the contractor or be called.

  • 1

    On signing the contract

    Define the period

    From what date it is counted, when the guarantee is returned, and whether it is reduced along the way.

  • 2

    On completion and handover

    The performance guarantee is replaced

    Document the completion date and the handover dates. The end of the period is derived from them.

  • 3

    During the warranty period

    Notice, opportunity, repair

    The client gives written notice and a proper opportunity. The contractor repairs and documents.

    Contract for Services Law, Sections 3 and 4

  • 4

    Before the guarantee expires

    Extension or a demand for payment

    An “extend or pay” demand must reach the bank while the guarantee is in force.

    CA 616/07

  • 5

    At the end of the period

    Return or accounting

    The guarantee or its balance returns to the contractor. A sum collected in excess is claimed in a restitution claim.

    CA 11123/03

RememberThe guarantee is security, not compensation. What was not due to the client under the contract has to be returned.

“Extend or pay”: may the client demand this?

Yes. Banks customarily limit a guarantee to a fixed period, sometimes a year at a time, and so a warranty guarantee that is meant to last for years has to be renewed again and again. A client who sees the expiry date approaching sends the bank a demand: to extend the guarantee, and if it is not extended, to pay under it.

In CA 616/07 the contractor was already in liquidation. The developer applied to the bank before the expiry date and demanded an extension for a further year, and alternatively payment. The bank extended without informing the liquidator, and the guarantee was called several months later. The District Court set aside the call, but the Supreme Court reversed the decision. It held that putting the choice is not a lack of good faith: a party who is entitled to demand immediate payment and offers the bank the more moderate option of an extension cannot be criticized for doing so. The alternative demand for payment, which was sent while the guarantee was in force, remained in place as the default.

Two practical conclusions. A client needs to keep a diary of the expiry dates and send the demand in time and in the wording the guarantee document requires, because payment under a guarantee is conditional on exact compliance with its terms. And a contractor who refuses to extend a guarantee he undertook to extend risks a call: in a decision of 2020 (LCA 5958/20) the Supreme Court refused to stop payment under a guarantee, in circumstances in which the contract provided that a failure to extend a guarantee gives a right to call it.

The client called the guarantee without justification. What can the contractor do?

Stopping the call is almost impossible. An autonomous bank guarantee is detached from the dispute between the parties, and the court will intervene only in a case of fraud or in “special circumstances” of extreme lack of good faith. A dispute over whether there were defects, whether they were repaired and who is responsible for them is not enough. An example the case law gives of special circumstances: a client who confirmed in writing that the works were completed and nevertheless demands payment under the performance guarantee.

But the call is not the end of the road. The Supreme Court held (CA 11123/03) that a party who took advantage of the independence of the guarantee and collected a sum to which he was not entitled under the underlying transaction holds the money “without a legal right”, and must return it under the law of unjust enrichment. This restitution does not prevent the call itself, otherwise the guarantee would lose its value, but it allows a monetary claim after it. In other words: the guarantee determines who holds the money while the parties litigate, not who is right.

The layerBetween whomWhat sets the periodWhat happens at its end
Liability under the Sale (Apartments) LawThe apartment buyer and the sellerThe Schedule to the Law: one to seven years from handover, according to the type of defect, plus three years of liabilityThe burden of proving the source of the defect passes gradually to the buyer
The contractor’s contractual liabilityThe client and the performing contractorThe contract, and alongside it the Contract for Services LawAccording to the contract. The liability does not depend on the existence of the guarantee
The warranty guaranteeThe bank and the clientThe guarantee document and its extensionsExpiry or return. After expiry the bank does not pay

Six rules, for the contractor and for the client

  1. Define the starting point. The handover of each apartment, the handover of all the apartments or a completion certificate: the difference can amount to years.
  2. Write a return mechanism. A defined date, and whether the guarantee is reduced in stages as the shorter warranty periods end.
  3. Set what precedes a call. Written notice, a period for repair, and a partial call according to the cost of repair.
  4. Document every call-out and every repair. The date of the notice, what was repaired, and written confirmation from the client or the resident.
  5. Track the expiry dates. The client sends a demand in time. The contractor asks, toward the end of the period, for written confirmation of the return of the guarantee.
  6. The guarantee was called? Draw up an account. How much the repairs actually cost, and what was collected beyond that. The difference is claimed.

If you are based abroad

Foreign contractors and suppliers who provided a bank guarantee for a project in Israel do not need to be in Israel to manage it. Our office can follow the expiry dates, correspond with the client and the bank, and conduct proceedings in Israel under a power of attorney signed before an Israeli consul, or before a local notary with an apostille.

Frequently asked questions

The guarantee expired and was not renewed. Has my liability as a contractor for defects ended?

No. The guarantee is security for the performance of the obligation, not the obligation itself. If the liability period in the contract is still running, the client may demand repair and sue, even without a guarantee in hand. The difference is that without the guarantee he will have to go to court in order to collect.

The warranty period in the contract has ended, and the client demands an extension of the guarantee because of open defects. Must I agree?

It depends on the contract. If the contract requires return on a particular date, a demand for an extension beyond it goes beyond the contract. But as long as the guarantee is in force, the client can demand that the bank pay under it, and the bank will pay if the terms of the guarantee document were met. It is therefore worth arriving at the end of the period with documentation of the repairs and with an orderly demand for return, and not waiting for the last week.

The client called the entire guarantee because of a small defect. Will I receive the difference?

If the call exceeded what was due to the client under the contract, you have a restitution claim for the balance. The burden of showing the extent of the defects and the cost of repairing them will arise in the proceeding, and so the documentation from the warranty period is the central evidence.

The contractor became insolvent during the warranty period. What happens to the guarantee?

This is exactly the situation for which it was given. The bank pays out of its own money, and its duty to pay does not depend on the contractor’s condition. In CA 616/07 the call of a warranty guarantee given on behalf of a contractor in liquidation was upheld. We discussed the calling of guarantees close to the opening of insolvency proceedings in our article on the autonomous bank guarantee.

I am an apartment buyer. Do I have a right in the warranty guarantee the contractor gave the developer?

No. The warranty guarantee is security in the relationship between the performing contractor and the client. Your rights to the repair of defects are against the party who sold you the apartment, under the Sale (Apartments) Law, and they do not depend on whether the developer holds a guarantee from the contractor. Nor should it be confused with the Sale Law bank guarantee, which secures the money you paid until handover and registration.

A warranty guarantee is about to expire, or a demand for payment has been received?

Our firm represents developers and contractors in drafting guarantee mechanisms, in managing the warranty period and in disputes over calls and restitution. With guarantees the deadlines are short, and so it is worth acting before the expiry and not after it. We represent clients throughout Israel and abroad, mostly by phone and video.

For an initial conversation: +972-2-509-0170
Adv. David Bodenheim, Partner, Head of Litigation at Bodenheim Gabriel & Co., represents developers, contractors and property owners in construction and real estate disputes in all courts. Our litigation practice. Bodenheim Gabriel & Co., 214 Jaffa Street, Jerusalem.

This article is intended for general information only and does not constitute legal advice or a substitute for it. Every case is examined according to the wording of the contract and of the guarantee document. Last updated: November 2026.

Main sources

  • Contract for Services Law, 5734-1974, Sections 3 and 4
  • Sale (Apartments) Law, 5733-1973, Section 4 and the Schedule
  • CA 616/07 Bank Mizrahi Tefahot Ltd. v. A.M. Turgeman Ltd. (in liquidation) (Supreme Court, February 24, 2010)
  • CA 11123/03 T.S.T. Building Contracting Company Ltd. v. State of Israel (Supreme Court, October 2, 2005)
  • LCA 5958/20 Y.D. Ashush Infrastructures Ltd. v. Alstom Israel Ltd. (Supreme Court, decision of October 22, 2020)
  • LCA 21381-09-25 Azorim Building (1965) Ltd. v. Biton (Supreme Court, December 25, 2025)
  • Eyal Zamir, Contract for Services Law, 5734-1974 (1994), Sections 3 and 4