The Autonomous Bank Guarantee in a Construction Project in Israel: When the Bank Must Pay, When a Call Can Be Stopped, and What Happens When the Contractor Collapses

קו אור יחיד מצייר בלילה מגן שבתוכו סימן שאלה מעל שולחן ישיבות עם כתב ערבות בנקאית ומנוף בנייה נשקף מהחלון, להמחשת חילוט ערבות בנקאית אוטונומית

By Adv. David Bodenheim, Partner, Head of Litigation | Published: November 9, 2026

The autonomous bank guarantee is the most common security in construction projects in Israel: the tender guarantee, the performance guarantee, the warranty guarantee, the advance payment guarantee. Its strength lies in the word “autonomous”: the bank pays on demand, without examining who is right in the dispute between the developer and the contractor. That is why the courts almost never stop a call: only serious fraud by the beneficiary or “special circumstances” of extreme bad faith justify an injunction, and an ordinary contractual dispute, even a well-founded one, is not enough. Whoever calls a guarantee unlawfully is not immune: he will be sued to return the money afterwards, but in the meantime the money will be with him. And in December 2025 the Supreme Court added an important rule: even when the contractor enters insolvency proceedings, a call that has been carried out will not be set aside as a “preference of creditors,” because the bank pays out of its own money. This is how the rules look from both sides of the table.

We accompany construction companies that deposit guarantees and developers and clients that hold them, so this article is written for both sides: for whoever receives a demand under a guarantee and must decide within days whether to run to court, and for whoever is considering calling a guarantee and needs to know when that is lawful, when it is wise and what a mistake costs.

Key points

  • Two principles define an autonomous bank guarantee: the principle of independence (the bank pays regardless of the dispute in the underlying transaction) and the principle of strict compliance (only if the demand meets exactly the terms of the guarantee document: amount, date, beneficiary, form of the demand).
  • When commercial parties require a bank guarantee, the assumption is that they intended an autonomous guarantee, unless the wording expressly ties it to the underlying transaction (the T.S.T. ruling).
  • Only two exceptions justify an injunction against a call: serious fraud by the beneficiary, or “special circumstances” of conduct that is especially grave, arbitrary, vindictive or in extreme bad faith. “The existence of a contractual dispute between the parties to the underlying transaction is not enough.”
  • Examples from the case law of special circumstances: a client that confirmed in writing that the works were completed and then demands payment under a performance guarantee; an underlying transaction whose invalidity is not in doubt.
  • A call that is contrary to the underlying transaction is not prevented, but gives rise to a right of restitution: whoever called more than he is owed will repay it in a monetary claim, sometimes with costs.
  • The parties may narrow by agreement the grounds for calling the guarantee (for example only under a judgment or an arbitral award), and then a call contrary to the condition is stayed. Failure to extend a guarantee that is about to expire is a recognized ground for calling it (the Ashush ruling).
  • In the contractor’s insolvency: a call carried out before the order commencing proceedings will not be set aside as a preference of creditors, because the bank pays out of its own money and not out of the company’s funds; the insolvency court may only stay temporarily a call that has not yet been carried out, for a short period, in order to check whether an exception applies (the Azorim ruling, December 25, 2025).

What makes a bank guarantee “autonomous,” and why does it matter so much?

An ordinary guarantee, under the Guarantee Law, is an accessory obligation: the guarantor is liable only if the debtor is liable, and can raise all the debtor’s defenses. An autonomous bank guarantee is built the other way round. The Supreme Court has described it as “an undertaking by the guarantor bank to pay the beneficiary of the guarantee a sum of money stated in that undertaking, when the conditions set for this in the guarantee document are met,” and in effect “a kind of undertaking to indemnify,” not a guarantee in the ordinary sense. Two features distinguish it: the principle of independence, under which payment “is not conditional on clarification of the disputes concerning the transaction” between the parties, and the principle of strict compliance, which requires “particular strictness as to the conditions required in the guarantee document for calling it.”

The reason the courts protect this independence so zealously is economic: a guarantee that can be held up every time there is an argument is not worth much. In the Supreme Court’s words, the purpose is “to increase stability and certainty in commercial life, by creating a certain, efficient and quick financial mechanism, which frees the beneficiary from the need to conduct legal proceedings in connection with the underlying transaction as a condition for receiving the secured payment.” The legal assumption is that when commercial parties choose a bank guarantee, they intend an independent guarantee, “unless it clearly emerges from its content that they intended to regard it as an ordinary guarantee” (CA 11123/03 T.S.T. v. State of Israel).

When can a call be stopped all the same?

The case law has recognized two exceptions, and both are applied “sparingly.” The first is the fraud exception: serious fraud on the part of the beneficiary, for example a demand that rests on forged documents. The second, and the more relevant in practice, is the special circumstances exception. The Supreme Court has defined it as “especially grave conduct by the beneficiary, even if it does not amount to fraud, or arbitrary conduct by the beneficiary in demanding payment under the guarantee, or conduct plainly driven by extraneous considerations, the exertion of pressure or vindictiveness.”

The sentence that decides the fate of most applications for an injunction is this: “To come within the special circumstances, the existence of a contractual dispute between the parties to the underlying transaction is not enough. For that, conspicuous unfairness in the performance of the contract is required.” In the Friron case the District Court granted an injunction against a call because it was persuaded, on prima facie evidence, that it was the beneficiary that had breached the agreement. The Supreme Court set the injunction aside: “Even if the court reaches a prima facie conclusion that one of the parties is the party in breach, this does not necessarily lead to the grant of a temporary order preventing the calling of the autonomous bank guarantee… Extreme bad faith is required.” The applicant was ordered to pay NIS 50,000 in costs (LCA 1084/04).

And what does count as special circumstances? The case law has given two clear examples: a client demanding payment under a performance guarantee “where he confirmed in writing to the other party that the works had been completed,” or a demand for payment “when the invalidity of the underlying transaction is not in doubt.” The common denominator: not “he breached and I am right,” but “he himself confirmed that he has no ground.”

A demand under an autonomous bank guarantee

What stops the bank, and what does not

According to the case law of the Supreme Court. The rule: the bank pays; the exceptions are narrow and applied “sparingly.”

May justify an injunction

The demand does not match the guarantee document

An amount higher than stated, a demand after expiry, a different beneficiary, a missing signature or required wording. The principle of strict compliance works in the customer’s favor, and this is the first check.

The beneficiary confirmed in writing that the obligation was performed

A completion certificate, a final approval, confirmation that all defects were repaired, and then a demand under a performance or warranty guarantee: the classic example of special circumstances.

The underlying transaction is void beyond doubt

An agreement cancelled by consent, or held invalid in a judgment, and the beneficiary goes on demanding payment.

The parties narrowed the grounds for calling it in the agreement

If it was agreed that the guarantee would be called only under a judgment or an arbitral award, a call based on an allegation of breach alone is stayed until a decision (Ashush).

Fraud or plain vindictiveness

False documents, a demand meant to apply pressure in another dispute, a call immediately after relations were severed with no ground at all.

Will not stop the call

“He is the one in breach, not me”

A contractual dispute, even a well-founded one with prima facie evidence, is not special circumstances. Friron: the injunction was set aside and the applicant ordered to pay costs.

“The amount is higher than the damage”

The amount of the damage is examined in the monetary claim after the call, not in an injunction. An excessive call gives rise to a right of restitution (T.S.T.).

“We have an arbitration or a mediation between us”

Not enough in itself, although in certain circumstances a call made in parallel with an arbitration may be regarded as special circumstances (Ashush).

“The contractor is insolvent”

A call that has been carried out will not be set aside as a preference of creditors, because the bank pays out of its own money. The insolvency court may stay temporarily, for a short time, only a call not yet carried out (Azorim, 2025).

“I did not extend it because I was sure we were finished”

Failure to extend a guarantee that is about to expire is an accepted ground for calling it in contracts, and the Supreme Court upheld a call on that basis (Ashush).

RememberAn injunction is sought before the bank has paid. After payment only a restitution claim remains, and that is a longer and more expensive road.

My guarantee was called unlawfully. What now?

The Supreme Court explained in the T.S.T. case the distinction that is important to understand: the independence of the guarantee protects the call itself, but not the money. “If the creditor took advantage of the independence of the right and collected from the guarantor, although he was not entitled to do so… the payment he collected is a gain without lawful right.” In other words, collection contrary to the underlying transaction “gives rise to a right of restitution,” but “does not prevent the calling of the guarantee itself.” Otherwise, “in every case in which the call was made contrary to the underlying transaction, it would be possible to prevent the call, and thereby to frustrate the independent standing and purpose of the bank guarantee.”

The practical meaning: a contractor whose guarantee was called unlawfully files a monetary claim for restitution, in which the underlying transaction is examined on its merits: who was in breach, what the real damage is, and what the relation is between the amount called and the damage. In the same proceeding interest and linkage from the day of the call can also be claimed, and in cases of an arbitrary call, costs. This is why a prudent beneficiary does not call a guarantee “to be on the safe side”: an excessive call is an expensive loan that will have to be repaid.

The contractor became insolvent: what happens to the guarantees?

This is the question that was decided in LCA 21381-09-25 Azorim v. Biton (December 25, 2025). A construction company deposited with a developer bank guarantees totaling about NIS 1.4 million to secure its obligations in two projects. When the developer learned that the company was about to enter insolvency proceedings, it gave notice that it was calling the guarantees, approached the bank, and the money was transferred to its account within days, a few days before an order commencing proceedings was given. The trustees applied to set the call aside under Section 219(a)(1) of the Insolvency and Economic Rehabilitation Law, the section that allows “an act conferring a preference on a creditor” done in the three months before the order to be set aside, and the District Court granted the application.

The Supreme Court reversed the decision. Section 219 requires three cumulative conditions, and the third is that the act resulted in the creditor “being repaid a larger part of his debt” than he would have received in the proceeding. With an autonomous bank guarantee, this condition “as a rule, is not met”: the bank pays the beneficiary out of its own money, whether the contractor is solvent or not, so the call does not take anything away from the creditors’ fund. At the same time the Supreme Court recalled the tool that does exist: the insolvency court may order “a temporary stay of the calling of autonomous bank guarantees,” in order to give the trustee time to check whether an exception applies, but “these are orders given for short periods only” and “before the guarantee is called.”

The lesson for developers and clients: a bank guarantee is precisely the security meant for a situation in which the contractor collapses, and whoever holds one must act according to the guarantee document before it expires and before a stay order is given. The lesson for contractors and trustees: the way to prevent an unlawful call in an insolvency setting is a quick application for a temporary stay before payment, with evidence of an exception, and not an application to set it aside afterwards.

Type of guaranteeWhat it securesWhen it is releasedThe typical risk
Tender guaranteeThat the winner will sign the contract and deposit a performance guaranteeOn signing the contract and depositing the performance guaranteeA winner that withdraws its bid
Performance guaranteeCompletion of the works according to the contract, the timetable and the qualityAt handover, usually against a warranty guaranteeA dispute over completion, delays, abandonment of the site
Warranty (quality) guaranteeRepair of defects in the warranty periodAt the end of the warranty period, after the reported defects were repairedThe client “forgets” to return it; a demand over defects that were repaired or not reported in time
Advance payment guaranteeRefund of an advance paid to the contractor before performanceWhen the advance is set off against the accountsA call after the advance has in fact already been set off
Sale Law guaranteeThe money of a buyer of an apartment from a developer (Sale (Apartments) (Assurance of Investments) Law)On registration of the rights or delivery as the Law providesA separate, consumer arrangement, not discussed in this article

Seven rules for drafting and managing guarantees in a project

  1. The wording of the demand. In an autonomous guarantee, “on first written demand, without your being required to give reasons or proof.” Any additional condition in the guarantee document, for example attaching an engineer’s certificate or an arbitral award, narrows the independence, sometimes on purpose and sometimes by mistake.
  2. Amount, linkage and validity. The expiry date is the most important date in the document. A client holding a guarantee that is about to expire demands an extension in writing a reasonable time in advance, and if it was not extended, that is a ground for calling it that the Supreme Court has recognized.
  3. Consistency between the agreement and the guarantee document. If the agreement provides that the guarantee will be called only after a warning or only under an arbitral award, the call is subject to that even when the guarantee document is silent (Ashush). Contractors: this is the place to obtain real protection; clients: this is the place to be careful of it.
  4. The chain of guarantees. A performance guarantee is replaced by a warranty guarantee at handover, and the warranty guarantee is released at the end of the warranty period. Document every replacement in a protocol, and state which defects are open.
  5. A demand that meets the principle of strict compliance. In a formal letter, to the right branch, in the stated amount, before expiry, signed by the beneficiary’s authorized signatories. A defective demand may be rejected by the bank, and if the guarantee has expired in the meantime, the damage is irreversible.
  6. Before calling: the question of price. A beneficiary that called more than the damage will be required to repay in a claim, with interest and sometimes costs. A proportionate and documented call is easy to defend; a full call “because it is possible” turns the client into a defendant.
  7. When a demand is received: a clock measured in days. Check compliance, check whether there is evidence of an exception (written confirmation of completion, cancellation of the transaction, fraud), and if there is, apply to the court before payment. If there is not, do not waste money on an injunction that will be refused with costs, but prepare the restitution claim.

If you live abroad

A foreign company or investor holding or providing a guarantee in an Israeli project works against the same clock of days. Our office can review the guarantee document and the demand, apply to the court where an exception applies and conduct the restitution claim for you, under a power of attorney, by phone and video.

Questions asked in the first conversation

The client did not pay my final account and is now demanding payment under the performance guarantee. Do I have an injunction?

Probably not, if that is the whole story. “He owes me” is a contractual dispute, and the Supreme Court has held that such a dispute, even with prima facie evidence, is not special circumstances. The useful check is a different one: whether the client confirmed in writing that the works were completed, whether the demand matches the guarantee document, and whether the agreement limits the grounds for calling it. If not, the remedy is a monetary claim for the account and the call together.

The warranty period has ended and the client is not returning the warranty guarantee. What do we do?

Demand in writing the return of the guarantee document, referring to the date the warranty period ended and to the protocol of repair of the defects. If the client tries to call it after the period has ended or over defects that were repaired and approved, this is exactly the example the case law has recognized as special circumstances. And in the meantime the guarantee costs you money at the bank every month, and that too can be claimed.

My contractor entered a stay of proceedings. Can I still call the guarantee?

In principle yes, as long as the demand matches the guarantee document and there is no court order staying it. The Supreme Court held in December 2025 that such a call will not be set aside as a preference of creditors. But the insolvency court may temporarily stay a call not yet carried out, so act quickly, precisely and in writing, and document the ground for the call.

Can the bank refuse to pay?

Only if the demand does not meet the terms of the guarantee document (the principle of strict compliance), or if there is a court order. The bank does not examine the underlying transaction and is not supposed to hear the customer’s arguments. An attempt “to persuade the bank” is usually a waste of the valuable days before payment.

We signed an arbitration clause. Can we demand that the guarantee wait for the arbitrator’s award?

It depends on the documents. If the agreement provides that calling the guarantee is subject to the arbitrator’s decision, yes. If not, the mere existence of an arbitration does not prevent a call, although the Supreme Court has noted that in certain circumstances a call made in parallel with an arbitration can be regarded as special circumstances. This is a question for the drafting of the agreement in advance, not for the dispute stage.

Received a demand under a guarantee, or considering calling one? The decision is measured in days

Our firm represents contractors, developers and clients in Israel in everything concerning bank guarantees: drafting guarantee documents and the provisions on calling them in the agreement, reviewing demands, urgent applications for injunctions where an exception applies, restitution claims after an unlawful call, and the release of warranty guarantees a client refuses to return. In the first conversation we will go over the guarantee document and the demand and tell you whether there is a ground to stop it, and if not, what the right way is to get the money back. We represent clients throughout Israel and abroad, mostly by phone and video.

For an initial conversation: +972-2-509-0170
Adv. David Bodenheim, Partner at Bodenheim Gabriel & Co., leads the firm’s complex litigation and civil-commercial disputes practice. A graduate of the litigation department of Herzog Fox & Neeman. Represents construction companies, developers and clients in construction contract disputes, guarantees and arbitrations. Our litigation practice. Read also: You Signed an Arbitration Agreement with a Private Beit Din: Confirming and Setting Aside an Award and The Demand Letter: When It Works and What It Must Contain. Bodenheim Gabriel & Co., 214 Jaffa Street, Jerusalem.

This article is intended for general information only and does not constitute legal advice or a substitute for it. The outcome of each case depends on the wording of the guarantee document, the agreement between the parties and the facts. Last updated: November 2026.

Main sources

  • Guarantee Law, 5727-1967; Insolvency and Economic Rehabilitation Law, 5778-2018, Section 219
  • LCA 21381-09-25 Azorim Building (1965) Ltd. v. Biton (Supreme Court, December 25, 2025)
  • LCA 5958/20 Y.D. Ashush Infrastructures Ltd. v. Alstom Israel Ltd. (Supreme Court, October 22, 2020)
  • CA 11123/03 T.S.T. Building Contracting Company Ltd. v. State of Israel, Ministry of Construction and Housing (Supreme Court, October 2, 2005)
  • LCA 1084/04 Friron Investment, Development and Building Company Ltd. v. Lucky Building and Development Ltd., 58(5) PD 535 (Supreme Court, 2004)
  • Avraham Weinroth, Bank Guarantee (2010, in Hebrew), Chapter 5: The Special Circumstances Exception