
By Adv. David Bodenheim, Partner, Head of Litigation | Published: November 2026
When the other side breaches a contract, Israeli law gives you three remedies: enforcement, rescission and damages. Damages are added to enforcement or rescission, or come in their place. But rescission cannot be drawn in every situation: a party who rescinds a contract without having a right to rescind, or without first giving an extension when one is required, is himself regarded as the party who breached the contract.
In the commercial disputes our office conducts, the outcome is often determined not on the day of the breach but in the weeks after it: what was written in the first letter, whether an extension was given, how long the party waited, and what was documented. This guide sets out the rules under the Contracts (Remedies for Breach of Contract) Law and the case law of the Supreme Court.
A breach is any act or omission that is contrary to the contract. Section 2 of the Remedies Law provides: “Where a contract has been breached, the injured party is entitled to claim its enforcement or to rescind the contract, and he is entitled to damages in addition to or in place of one of the said remedies”. Enforcement and rescission contradict each other, and so a choice has to be made between them. Damages can be added to either.
Enforcement is a demand that the contract be performed as written. Under Section 3 the injured party is entitled to it, unless one of four exceptions applies: the contract cannot be performed; enforcement would compel the doing or acceptance of personal work or a personal service; carrying out the order requires an unreasonable degree of supervision by the court or the Execution Office; or enforcement is unjust in the circumstances. Rescission releases both parties from the contract and obliges each of them to return what he received. Damages are intended to place the injured party, in financial terms, in the position he would have been in had the contract been performed.
The Law distinguishes between two kinds of breach. A fundamental breach is a breach that the parties agreed in the contract would be fundamental, or a breach such that a reasonable person would not have entered into the contract had he foreseen it and its consequences. For such a breach it is possible to rescind without waiting (Section 7(a)). For any other breach, the injured party may rescind only after he gave the party in breach an extension and the contract was not performed within a reasonable time, and even then not if the rescission is unjust in the circumstances (Section 7(b)).
The Supreme Court held in the Bashma case (2013) that as a rule, absent special circumstances, a short delay in performing an obligation, and in particular a monetary obligation, is not a fundamental breach, because it is relatively easy to cure. There the balance of the consideration was paid a day or two late, without any damage being caused, and the sellers hurried to rescind. The court refused to give its approval to “an injured party lying in wait for an opportunity to rescind”. Justice Amit added a rule of thumb: when there is doubt, the tendency is to classify the breach as not fundamental.
Even an agreed fundamental breach is not an absolute licence. In April 2026 the Supreme Court held, in the Jacobs case, that insisting on immediate rescission may in exceptional cases be regarded as a lack of good faith. There a seller rescinded the contract a few days after the last date for payment, although he himself had earlier breached a fundamental undertaking and the buyers needed a very short time. It was held that he should have given an extension, and that the rescission was unlawful.
This is the central trap. In the Deljo case (2010) the client under a long-term maintenance contract rescinded it, alleging fundamental breaches, and it was held that it had no ground to do so. The Supreme Court adopted the words of the scholars Shalev and Adar: a party who “repudiates a valid contract, and notifies the other of its ‘rescission’, is nothing but a party in breach of that contract. This is so even if the ‘rescinding party’ acted in good faith”. The result: the other party may demand enforcement or rescind himself, and claim damages.
The same happened in the Bashma case: the sellers who rescinded because of a two-day delay were ordered to complete the sale, and in addition to pay the buyer the liquidated damages set in the contract, ten percent of the consideration. Those who hurried to rescind found themselves paying the compensation they had sought to collect.
Breach of contract
The three remedies, and what each requires
Under the Contracts (Remedies for Breach of Contract) Law, 5731-1970
Enforcement
Sections 2 and 3
Rescission and restitution
Sections 6 to 9
Damages
Sections 10 to 15
Under Section 8, rescission is made by notice to the party in breach “within a reasonable time” after the injured party learned of the breach, and if an extension was given, within a reasonable time after it passed. In the Shufersal case (2011) the Supreme Court explained that the requirement protects the reliance of the party in breach, and that an injured party who did not exercise the right in time loses it. But the test is flexible: a few days may be an unreasonable time, and several years may be reasonable. There a rescission sent three years after the breach was upheld, because it was not proved that the timing caused the party in breach any damage.
And what happens to a party who put up with the breach for years? In the Micro Balanced Products case (2003) a manufacturer tolerated for fourteen years purchases that were below the minimum set in the distribution contract, and then rescinded it. The Supreme Court held that it had not waived its right, but that before rescinding it had to give a clear extension, even though the breach was defined in the contract as fundamental. An extension, it was held, is not silent patience: “the party in breach must understand that he has received an extension to perform the obligation, and that if he does not use this extension the contract will be rescinded”.
Section 10 entitles the injured party to damages for damage caused by the breach and its consequences, which the party in breach foresaw or should have foreseen, at the time the contract was made, as a probable result of the breach. Both the existence of the damage and its amount have to be proved. In the Shufersal case neither expectation damages nor reliance damages were awarded, because the damage was not proved. By contrast, in the Deljo case the Supreme Court upheld compensation for loss of profits that was set in part by way of estimate: when it is clear that real damage was caused and it is difficult to quantify it precisely, the court has discretion to assess it on the basis of objective data.
Three rules complete the picture. Damages without proof of damage: when an obligation to supply an asset or a service was breached and the contract was rescinded, the injured party is entitled to the difference between the contract price and the value on the day of rescission; when a monetary obligation was breached, he is entitled to interest on the sum in arrears (Section 11). Liquidated damages: will be awarded as set in the contract, but the court may reduce them if they were set without any reasonable relation to the damage that could have been foreseen in advance (Section 15). Mitigation of damage: the party in breach is not liable to compensate for damage that the injured party could have prevented or reduced by reasonable means (Section 14). In the Deljo case seven years remained on the contract, but the compensation was calculated for two years only, on the assumption that in that time the company could have found other work.
| The judgment (Supreme Court) | What happened | What was held |
|---|---|---|
| CA 7403/11 Bashma (2013) | A delay of a day or two in paying the balance of the consideration, and the sellers rescinded | Not a fundamental breach. Rescission without an extension was a breach. Enforcement and liquidated damages for the buyer |
| CA 8588/06 Deljo (2010) | A long-term service contract was rescinded on an allegation of fundamental breaches that were not proved | An unlawful rescission is a breach. Compensation for loss of profits, limited because of the duty to mitigate |
| CA 8741/01 Micro (2003) | Rescission of a distribution contract after fourteen years of putting up with the breach | Even for an agreed fundamental breach, a clear extension was required before rescission |
| CA 512/08 Shufersal (2011) | A tenant rescinded a contract three years after the breach | The rescission was made within a reasonable time in the circumstances. Mutual restitution. No compensation without proof of damage |
| CA 6275/23 Jacobs (2026) | Immediate rescission because of a short delay, after an earlier breach by the rescinding party | Strict insistence on the right to rescind was a lack of good faith. An extension was required |
Foreign companies and individuals with a contract governed by Israeli law do not need to be in Israel to enforce it. Our office can send the warning letter, conduct the negotiations and the court proceedings, and act under a power of attorney signed before an Israeli consul, or before a local notary with an apostille.
Not necessarily. Under Section 6, a sweeping clause that makes breaches fundamental without distinguishing between them is valid only if it was reasonable at the time the contract was made. By contrast, a defined list of undertakings marked as fundamental will usually be respected. In the Jacobs case Justice Grosskopf suggested, in an obiter remark, that a clause should be regarded as sweeping only when the parties bundled different breaches together without distinguishing between serious and minor ones.
Yes. Section 2 provides that damages come in addition to rescission or enforcement, or in their place. After rescission each party returns what he received, and the injured party may also claim the damage caused to him, subject to the duty to prove it and the duty to mitigate.
Not automatically. In the Shufersal case the Supreme Court held that as long as the contract has not been rescinded, each party must continue to perform his obligations, and that the mere existence of a breach does not by itself give rise to a right to reduce a payment unilaterally. The tenant who reduced the rent on its own initiative was ordered to pay the difference. Before withholding a payment, check whether the contract or the law gives such a right.
It depends on what can be shown. Without proof that damage was caused, no compensation will be awarded. But when it is clear that real damage was caused and the difficulty is only in quantifying it, mainly for future loss of profits, the court may assess the sum. Liquidated damages set in the contract save the need to prove the damage.
Sometimes. Section 18 provides that a breach is not a ground for enforcement or damages if it resulted from circumstances that the party in breach did not know of and did not have to know of or foresee at the time the contract was made, could not have prevented, and performance became impossible or fundamentally different from what was agreed. Even then the court may order each party to return what he received.
Our firm represents companies, developers, contractors and business owners in contract disputes, from the warning stage to the conduct of the proceedings in court. The first step often determines everything that follows. We represent clients throughout Israel and abroad, mostly by phone and video.
For an initial conversation: +972-2-509-0170This article is intended for general information only and does not constitute legal advice or a substitute for it. Every case is examined on its own circumstances and according to the wording of the contract. Last updated: November 2026.