By Adv. Mike Gabriel, Partner, Head of Real Estate | Published: November 2, 2026
If you paid through the payment voucher book into the project’s financing account, the money you paid on account of the price of the apartment is secured: usually by a Sale Law bank guarantee, with the VAT component refunded on a separate track. The financing bank will choose whether to complete construction or return your money. Money you paid outside the vouchers, or directly to the building contractor for upgrades, is usually not secured by the guarantee, and it is claimed in the insolvency proceeding like any creditor’s claim.
The collapse of a construction company is one of the hardest moments for apartment buyers. You paid large sums, construction has stopped, and a notice arrives about a receiver or an order commencing proceedings. The law was built for exactly this situation, but its protection depends on the details: how you paid, whom you paid and what the contract says. It is worth checking these details in the first weeks, before deadlines pass.
The Sale (Apartments) (Assurance of Investments of Purchasers of Apartments) Law, 5735-1974 provides that a seller shall not receive from the buyer “an amount exceeding seven percent of the price” unless it has given the buyer one of five securities: a bank guarantee or a guarantee from another guarantor, an insurance policy, a mortgage, a caveat with no prior charge, or transfer of ownership (Section 2). In projects with bank financing the common security is a guarantee: the buyer pays by voucher into the project account, and the payment is “an irrevocable instruction” to the bank to provide a guarantee within 14 business days (Section 3B).
It is important to know: beyond the payment rates set in the regulations according to the stages of construction, the seller may receive money only if it gave a guarantee or an insurance policy (Section 3). A caveat alone is enough only for payments up to those rates.
The guarantee secures the refund of “all the money the buyer paid him on account of the price,” without the VAT component. It is triggered when the seller cannot transfer the apartment to you because of an attachment, a stay of proceedings order, a receiving order, a winding-up order or the appointment of a receiver, or when “an absolute impediment” to delivering the apartment to you has arisen. Cancellation of the contract in itself is not regarded as an absolute impediment. The VAT component is refunded to you by a Ministry of Finance fund, through whoever gave the guarantee, when the guarantee is called (Section 3C2).
Not on every breach of the contract. The Supreme Court held in 2004, by majority, that the guarantee secures delivery of the apartment or the return of the money, and not every term in the contract: “As long as it can still be called an ‘apartment,’ and it can be transferred, the guarantee cannot be called” (the Ovadia case). In 2012 Justice Joubran added in the Supreme Court, in a position also adopted in a 2026 judgment, that this is not a guarantee “on first demand”: one looks at the purpose of the Law, which is to protect the buyer from being left with neither an apartment nor money (the Biner case).
A question that is still open is a very long delay, when a receiver has been appointed but the project continues. In 2025 a Supreme Court justice stayed a District Court judgment that allowed some of the buyers to call guarantees in such a situation. She wrote that the issue “raises a question worthy of examination,” and that there is a difficulty in calling guarantees for only some of the buyers while the project is being completed. The proceeding ended without a decision. In August 2026 a judge of the Tel Aviv District Court allowed two families to cancel their contracts and call the guarantees after the appointment of a receiver and a long delay, in an approach she herself presented as new. This is a possible argument, but the outcome is not assured.
In October 2026 the Supreme Court gave a guiding judgment on this question (CA 3301/23). The decision whether to pay out the guarantees or complete the project is a business decision of the bank. But if the bank chooses to complete, it cannot choose which parts of the contracts to perform: there is no “selective completion of a project.” The buyers’ compensation for delay from the date the proceeding to enforce the charges began is regarded as expenses of the proceeding, and generally ranks ahead of the bank’s rights. Compensation for delay from the period before that is an ordinary debt of the company.
In the same judgment the Supreme Court noted, in passing, that the case law has recognized a duty of care of the financing bank toward the buyers, which may found liability mainly where reliance on negligent representations by the bank, or negligence in supervision, is proved. Still, the Supreme Court rejected the argument that the bank bears, by default, a general duty to update the buyers on the state of the project. So do not wait for a notice from the bank: check the state of the guarantees on your own initiative.
One more thing, about set-off: if you waived a right of set-off in the contract, as a rule you will not be able to set off compensation for delay against the balance you owe the bank (CA 2457/24). But when the bank chooses to complete construction, the Supreme Court held in 2026 that compensation for delay for the period after the appointment of the receiver can be set off against the balance (CA 3301/23).
The development company collapsed
What to do, step by step
Most of the damage is caused by deadlines that pass and documents that were not collected in time.
Immediately
Collect the documents
The contract and its appendices, the vouchers, the original guarantees, the transfer confirmations, the upgrade orders and a Land Registry extract. And from the moment of the notice of collapse, do not pay another shekel to anyone without advice.
Sections 2 and 3B of the Assurance of Investments Law
In the first weeks
Check every payment
Every payment by voucher should have a guarantee. A missing guarantee is demanded from the financing bank in writing.
Section 3B(d)-(e)
Within 6 months of publication of the order
File a proof of debt
For every amount not secured by a guarantee, and for compensation for delay from the period before the order. Filing is usually online. The trustee may extend the time only if you could not file in time and it is just to allow it.
Section 210 of the Insolvency Law; Regulation 120
When the bank decides
Completion or payout
On completion, follow the timetable and the compensation for delay. On payout, submit the guarantees and receive the VAT back as well.
CA 3301/23; Section 3C2
After the trustee’s decision
Appeal, if needed
A decision on the proof of debt can be appealed to the court within 45 days of receiving it.
Section 215; Regulation 131
Not necessarily lost, but usually not secured by the guarantee. The Law provides that the seller shall receive the payments only by means of the voucher book, and receiving a payment in another way is even an offense (Sections 3B(d) and 4(b)(2)). The Supreme Court repeated this in 2026: every buyer “is obliged to pay the consideration … only by means of these vouchers.” Money paid in cash, to another account or to the company’s owner is usually not secured by the guarantee. The Tel Aviv District Court even held in 2023, under an express clause in the contract, that NIS 650,000 paid to the developer’s owner and not to the project account was not considered a payment on account of the apartment.
For upgrades and additions, the difference is whom you paid and under which contract. The “price of the apartment” in the Law is “any amount the buyer undertook to pay the seller in the sale contract in connection with the purchase of the apartment.” On the wording of the definition, upgrades you undertook to pay the seller for under the sale contract and that were paid by voucher are part of the price. There is no Supreme Court ruling on this. According to the view in the literature, a payment for upgrades made directly to the building contractor is not secured by the guarantee, “since it is not transferred to the project account” (Weinroth, Bank Guarantee). These amounts are claimed in the insolvency proceeding of whoever received them, so it is important to keep the upgrade orders, the receipts and the correspondence.
This is the common situation in large projects, and also in urban renewal (Pinui Binui) projects: the company selling the apartments is a development company, and the construction itself is carried out by a building contractor. When the building contractor collapses, the developer usually removes it from the site, gives notice of a fundamental breach and brings in another contractor to complete construction. For the buyers this is better than the collapse of the developer itself, but it has several consequences worth understanding.
The contract and the guarantees are not affected. Under the Assurance of Investments Law, a “seller” is whoever sells an apartment that it built “itself or through another person.” In other words, the developer remains responsible to you for delivering the apartment even when the contractor has changed. The guarantees you received from the financing bank were given against payments to the developer, and the events that trigger them are orders against “the seller or against the owner of the land,” not against the building contractor. So there is no reason to rush to call them, and no possibility of doing so merely because the contractor collapsed.
The delay in delivery. Replacing a contractor in the middle of construction almost always postpones delivery by months. Compensation for the delay is due from the developer under the Sale (Apartments) Law, and the collapse of its contractor is usually the developer’s risk, not yours.
The money you paid to the building contractor. This is where the real damage lies. In many projects the buyers are referred to order the upgrades to the apartment, such as a kitchen, flooring or electrical additions, directly from the building contractor, and to pay it. That money did not go through the vouchers or into the project account, so there is usually no guarantee for it. If the contractor collapsed before carrying out the upgrades, you are its creditors: file a proof of debt with the trustee within six months of publication of the order commencing proceedings (Section 210(a) of the Insolvency Law), with the upgrade order, the receipts and the correspondence. Sometimes the court orders that the company continue to be operated for a limited period in order to find it a buyer, and then too the proof of debt is filed on time.
Is the developer also liable for this money? There is no binding precedent of the Supreme Court on this, and the answer depends on the facts: whether it was the developer that referred you to pay the contractor, what the sale contract and the upgrades appendix say, whether the building contractor was presented as acting on behalf of the developer, and what the developer knew about the contractor’s condition when you went on paying it. These are questions worth clarifying before giving up, and in any event rights should be preserved in writing against the developer and not only against the trustee.
Upgrades not yet carried out. The new contractor is not bound by orders you placed with the previous contractor. Ask the developer in writing, as early as possible, for a clear notice: which upgrades were actually carried out, which were not, who will carry them out now and at what cost. If you are required to pay again for the same upgrades, that payment is part of the damage that is claimed.
| How you paid | Secured by the guarantee? | What to do |
|---|---|---|
| By voucher, into the project account, and there is a guarantee | Yes, the money paid on account of the price. The VAT is refunded separately | Keep the original guarantee and wait for the bank’s decision: completion or payout |
| By voucher, but the guarantee was not delivered | Payment by voucher obliges the bank to provide a guarantee | Demand the guarantee from the financing bank in writing, immediately |
| Outside the vouchers: cash, another account, to the owner | Usually not | A proof of debt to the trustee, with all the supporting documents |
| Directly to the building contractor, for upgrades | According to the view in the literature, no | A proof of debt in the proceeding of whoever received the money. Check what the contract says about upgrades |
| A project without bank financing, with a caveat | The caveat protects, but a payment beyond the rates in the regulations should have been secured by a guarantee or insurance | Stand on your rights against the trustee and against later creditors, and check what was paid beyond the rates |
Against most creditors, yes. Section 127(b) of the Land Law provides that a caveat registered before an attachment, before a winding-up order or before the appointment of a receiver protects the buyer’s rights after them as well, subject to the fact that a ground for cancellation that would have stood because of the winding-up also stands against the buyer. The Supreme Court has held that the caveat gives its holder priority over the creditors of whoever went bankrupt (CA 3042/19, 2020), and in a panel of seven justices held, in the context of an attachment, that a buyer who paid the full price prevails over a creditor of the seller who imposed a later attachment, even when no caveat was registered in the buyer’s favor (the Aharonov case, 1999). Whether you will receive the apartment itself from the trustee, and what the position is when you paid only part of the price, depends on the circumstances and has not been finally decided.
Against the financing bank the picture is different. The bank usually has a charge on the whole project that precedes your caveat, and your protection against it is the guarantee, together with a notice the bank gives under the Law: the charge will not be realized out of your apartment, among other things on condition that construction was completed, the apartment was delivered and “the full price of the apartment was paid to the seller in accordance with the voucher book” (Section 2C). This is another reason to pay only by voucher.
Buyers abroad often hear of a developer’s difficulties late, and the six-month period for a proof of debt runs regardless of where you live. Our office can collect the documents, deal with the financing bank and the trustee, and file for you, and where your signature is needed in Israel, act under a power of attorney signed before an Israeli consul, or before a local notary with an apostille.
Usually not, as long as there is no order or absolute impediment to delivering the apartment, because the guarantee secures the apartment and not the timetable. For the delay, compensation is due under the Sale (Apartments) Law. In such a situation it is worth checking whether there is a ground to cancel the contract, and what the consequences of cancellation are for the guarantees.
Yes, but not from the guarantee. Since 2017 the guarantee does not include the VAT component, and when it is called, a Ministry of Finance fund refunds it to you through the bank or the guarantor (Section 3C2).
Under the Supreme Court’s judgment of October 2026, compensation for delay from the start of the proceeding to enforce the charges generally ranks ahead of the bank’s rights, and can be set off against the balance of the price. Compensation for the period before that is an ordinary debt of the company, for which a proof of debt is filed.
Yes, even if the developer goes on building. Check whether you paid anything directly to the contractor, and if so, file a proof of debt with the trustee within the time limit, usually through the online system of the Commissioner of Insolvency Proceedings. At the same time, write to the developer and ask for a notice on the state of your upgrades and on the new timetable. Whoever paid the contractor nothing is usually not its creditor, but it is worth following the timetable and the compensation for delay.
Your contract is with the developer, and it is responsible for delivering the apartment to you and for compensating for delay under the Law. Money you paid directly to the building contractor is claimed first of all in its insolvency proceeding. Whether it can also be demanded from the developer depends on the circumstances: who referred you to pay the contractor, what the sale contract and the upgrade order say, and what the developer knew. The documents determine the answer, so keep all correspondence.
Our firm represents apartment buyers against developers, financing banks and trustees: reviewing the securities, demanding that guarantees be provided, proofs of debt and compensation for delay. In the first conversation we will go over the contract and every payment you made. We represent clients throughout Israel and abroad, mostly by phone and video.