A Pinui Binui or TAMA 38 Agreement in Israel: What an Apartment Owner Checks Before Signing

קו אור יחיד מצייר בלילה בניין ישן נמוך ומעליו מתאר של בניין חדש וגבוה, ולידם דף עם שורת חתימה, להמחשת הסכם פינוי בינוי או תמ"א 38

By Adv. Mike Gabriel, Partner, Head of Real Estate | Published: November 2026

Before signing an urban renewal agreement in Israel, seven things are checked: what exactly you receive and whether the neighbors receive the same, what securities exist if the developer fails, where you live during construction and who pays, what the timetable is and when you can leave, who bears the taxes, who represents you, and what happens to the apartment if something changes in the family. The law gives apartment owners several protections even before signing: a meeting and a key-terms document, a duty of disclosure on anyone acting for the developer, and a time limit on the validity of the transaction. But the law does not draft the agreement. What is not written in it is very hard to demand afterwards.

Our firm accompanies apartment owners, owners’ committees and developers in urban renewal (Pinui Binui) and TAMA 38 transactions, from the organizing stage through delivery of the new apartments and their registration. The agreement is a document of dozens of pages that is signed once and accompanies the building for years. Whoever knows what to look for in it reads it differently.

Key points

  • Before a first transaction is signed in the building, the developer must hold a meeting of the apartment owners and give all of them a key-terms document. If a transaction was signed without a meeting or without the document, a majority of the apartment owners may cancel it as long as 40% of them have not signed it (Section 5B of the Strengthening Law, which refers to Section 1A of the Pinui Binui Law).
  • Whoever acts on behalf of the developer, receives consideration from it, or whose fee depends on the transaction must say so in the first approach and in the agreement itself, and must report any non-negligible difference in consideration between apartment owners. A breach is a ground for withdrawing consent, even after signing (Section 5E of the Strengthening Law).
  • The validity of the transaction is limited in time. In TAMA 38, three dates are examined from the day of the first transaction: 18 months for half of the apartment owners to sign, three years to reach the required majority, and three and a half years for a building permit application to be accepted for processing (Section 5C).
  • Consent to work on the common property is given in writing and verified by a lawyer (Section 7). The apartment owner is entitled to receive the documents of the transaction he or she signed.
  • The law defines when refusing a transaction is reasonable: a transaction that is not economically worthwhile, no alternative housing, no adequate securities, special personal circumstances, adaptations for a person with a disability and alternatives for an elderly owner (Section 2(b) of the Pinui Binui Law). These are exactly the clauses that are checked in the agreement.
  • Equality between the apartment owners is a central test in the case law. It is examined according to what is written in the agreement, against what will actually be built.

What must the developer do even before anyone signs?

The law addresses the moment before the first signature, because that is where most of the dependence is created. The developer must convene the apartment owners, or take part in a meeting of theirs, and give each of them a document that sets out the key terms of the offer. After the first signature it must notify all the apartment owners, and it must give everyone who signed the transaction documents or a true copy of them.

Alongside this, a duty of transparency applies to intermediaries. An organizer, a broker or an adviser who acts on behalf of the developer, receives money from it, or whose fee depends on the transaction going ahead, must state this clearly in the very first approach. That way the apartment owners know who is talking to them. And if an apartment owner signed in circumstances of abusive signing, the Commissioner for residents’ complaints in urban renewal may determine that the transaction is void.

The consideration: what do you receive, and what does the neighbor receive?

The first question is economic: whether the transaction is worthwhile. In Pinui Binui, apartment owners holding the share set in the law may ask the Director of the Governmental Authority for Urban Renewal to appoint a Pinui Binui appraiser to examine whether it is worthwhile, and the appraiser’s determination creates a presumption. The Supreme Court has made clear that this is examined objectively, and that “the apartment owners are entitled to fair and reasonable consideration, but not necessarily to an equal division of the project’s profits between them and its developers” (CA 3511/13). In other words, the question is not how much the developer earns, but what you receive.

The second question is equality. When the Supreme Court considered a TAMA 38 agreement that a minority opposed, it listed the questions that are examined: whether the plan objectively benefits all the residents, whether it materially harms the minority, whether it was adopted in bad faith or in a conflict of interest, and whether equality between the residents is maintained (LCA 1002/14). In October 2026 the Tel Aviv District Court approved a Pinui Binui transaction despite the opposition of four apartment owners, among other things after examining a claim about a gap between the area of the existing apartment as written in the agreement and its area according to the building permit. The court noted that unfair treatment or a lack of equality can justify a refusal, even though they do not appear in the statutory list (Civil Case 25510-11-24). This is a District Court ruling, and it shows where the disputes arise.

So in the agreement you check: the area of the new apartment and the method of measurement, the floor and the orientation, the balcony, the parking space and the storage room, the technical specification, and the mechanism for choosing between the apartments. And you check that there is a clause requiring the developer to give all the apartment owners any benefit it gave to one of them.

An urban renewal agreement

Three layers of protection

The law gives the floor. The agreement sets the terms. The securities are what remains if the developer fails.

01The law

What you are owed without asking

  • A meeting and a key-terms document
  • Disclosure of who acts for the developer
  • A time limit on the validity of the transaction
  • A written signature, verified by a lawyer

Sections 5B, 5C, 5E and 7 of the Strengthening Law

02The agreement

What must be demanded and drafted

  • The consideration, the specification and equality
  • Rent and alternative housing
  • Timetable, compensation and exit points
  • Taxes, levies and expenses on the developer

Section 2(b) of the Pinui Binui Law; LCA 1002/14

03The securities

What remains if the developer fails

  • A guarantee for the value of the new apartment
  • A guarantee for the rent
  • Guarantees for taxes, registration and the warranty period
  • Bank financing supervision of the project

Section 2(b)(3) of the Pinui Binui Law; CA 3301/23

RememberThe consideration is checked on the day of signing. The securities are felt only on the day something goes wrong.

The securities: what protects you if the developer fails?

An apartment owner in urban renewal hands the developer his or her most valuable asset, and receives in return an undertaking for an apartment that has not yet been built. That is why the law provides that refusing a transaction in which adequate securities were not offered is a reasonable refusal. The law does not specify what the securities are, and that is a matter for the agreement. The customary securities are a guarantee for the value of the new apartment, a guarantee for payment of the rent during construction, a guarantee for payment of the taxes and levies the developer took upon itself, a guarantee for registration of the new condominium, and a guarantee for the warranty period.

It is important to understand what each guarantee covers. In a judgment of October 2026, which dealt with a strengthening-and-addition project that ran into difficulties, the Supreme Court repeated that a guarantee under the Sale Law is meant to prevent a situation in which one is left with no apartment and no money, and does not secure the developer’s other obligations, including the date (CA 3301/23). The meaning for an existing apartment owner: delay, rent and taxes need a security of their own, with clear conditions for calling it. You also check who is financing and supervising the project, and what has been provided for a case in which the developer is replaced.

The clause in the agreementWhat is checked
The considerationArea, floor, orientation, parking, storage and specification. The mechanism for choosing apartments. A clause equalizing terms between all apartment owners
The construction periodThe amount of the rent and how it is updated, moving costs, from when and until when it is paid, and what happens when construction runs long
TimetableDates for signatures, for the plan, for the permit, for vacating and for delivery. Compensation for delay. A right to cancel when a key date is not met
SecuritiesWhich guarantees, for what amount, when they are delivered, what the conditions for calling them are and when they are returned
Taxes and expensesCapital gains tax, purchase tax, betterment levy, VAT, legal fees and registration fees: who bears each one, and what happens if an exemption is not granted
ChangesWhat the developer may change in the design without consent, and what requires the approval of the owners’ committee or of each apartment owner
Transfer of rightsWhether the developer may transfer the project to another, and on what conditions. Whether an apartment owner may sell the apartment midway
RegistrationRegistration of the new condominium, the bylaws and the attachments, and the timetable for registering the apartment in your name

The timetable: when can you leave?

The most common risk in urban renewal is not that the developer will collapse, but that nothing will happen. Apartment owners sign, a caveat (warning note) is registered in favor of the developer, and the building stays stuck for years. The law gives a partial answer: the validity of the transaction is limited, and the dates are counted from the day the first transaction in the building was signed. In TAMA 38 it is examined whether the developer contracted with half of the apartment owners within 18 months, whether it reached the required majority within three years, and whether a permit application was accepted for processing within three and a half years. In Pinui Binui a parallel mechanism applies, with dates of its own.

The agreement needs to complete the law: a date for each stage, defined conditions precedent, a clear right to cancel when a condition has not been met, and an undertaking to delete the caveats when the transaction ends. An irrevocable power of attorney given to the developer or its lawyer should be limited to the actions the agreement permits.

Tax, elderly owners and personal circumstances

Tax. The sale of the old apartment to the developer is exempt from tax on the conditions in the Real Estate Taxation Law, among them that the consideration is one replacement apartment and that its value does not exceed the ceiling that has been set. Additional cash consideration, a unit that is not used as a residence, and an owner who holds several apartments in the compound are situations the Law deals with separately. That is why the agreement provides who pays if the exemption does not apply, and does not settle for the assumption that it will.

Elderly owners. An elderly apartment owner who lives in the apartment must be offered an alternative in addition to the replacement apartment, at the developer’s choice from among the alternatives in the law, such as a move to a retirement home, two small apartments, or a small apartment with an additional payment. For those aged 75 and over, broader protection was added in 2023. In TAMA 38, an elderly owner or a person who is permanently housebound must be offered alternative housing for the period of the works.

Disability and personal circumstances. Alternative housing and a replacement apartment for a person with a disability must include adaptations. Special personal circumstances are recognized in the law, but the Supreme Court has made clear that only in rare cases will they justify a refusal. Whoever has a special need raises it in the negotiations, not after them.

Six steps before signing

  1. Choose an owners’ committee and a lawyer of your own. The apartment owners’ lawyer is chosen by the apartment owners and acts for them, even when the fee is paid by the developer. It is worth making sure of this in writing.
  2. Demand a meeting and a key-terms document. This is a statutory right, and it is the basis for comparing offers from different developers.
  3. Check the developer. Projects it has completed, its financial strength, who the building contractor is and who is financing the project.
  4. Obtain an appraiser’s opinion. On the value of the apartment today, on the value of the consideration and on whether the transaction is worthwhile.
  5. Negotiate as a group. The agreement is identical for everyone, and any change given to one must be visible to all.
  6. Sign only a final and complete version. With all the appendices, before a lawyer who verifies the signature, and receive a signed copy.

If you live abroad

Owners who live abroad are often the last to hear that their building is being signed up. You do not need to fly in to take part: our office can review the offer and the agreement for you, represent you before the owners’ committee and the developer, and where your signature is required in Israel, act under a power of attorney signed before an Israeli consul, or before a local notary with an apostille.

Frequently asked questions

A representative of the developer is going from apartment to apartment collecting signatures. Do we have to sign now?

No. Before a first transaction is signed in the building, the developer must hold a meeting of the apartment owners and hand over a key-terms document. Whoever approaches you must say whether he or she acts on behalf of the developer or is paid by it. A transaction signed without a meeting can be cancelled by a majority of the apartment owners, as long as 40% of them have not signed it.

We signed years ago and nothing has moved. Are we bound to the developer?

Not necessarily. The validity of the transaction is limited by law, and the dates are counted from the day of the first transaction in the building. The agreement itself usually also sets dates and conditions precedent. Both are checked, together with the state of the caveats that were registered.

A neighbor received an extra from the developer that the others did not. What can be done?

Whoever acts on behalf of the developer must report to the apartment owners any non-negligible change in the consideration of one apartment owner compared with the others. Breach of the duty is a ground for withdrawing consent. Equality between the apartment owners is also one of the tests the court and the Superintendent of Land Registration examine when asked to impose the transaction on someone who refuses.

Who pays the capital gains tax and the betterment levy?

The sale to the developer is exempt from tax on the conditions in the Law, and in the customary agreements the developer bears the taxes and levies that apply because of the transaction. What matters is to check what has been provided for a case in which the exemption does not apply in full, for example when there is cash consideration or several apartments.

I oppose the transaction. What can be done to me?

If a special majority of the apartment owners has agreed and the refusal is not reasonable, in Pinui Binui the court may order the refusing owner to pay damages, or approve the transaction and appoint someone to sign in his or her name. In TAMA 38 the Superintendent of Land Registration may approve the work. We set this out in the article on the holdout owner.

My mother is 80 and lives in the apartment. What is she entitled to?

An elderly apartment owner who lives in the apartment must be offered an alternative in addition to the replacement apartment, and for those aged 75 and over the protection is broader. The alternatives also have tax consequences, so the choice between them is made together with the family and before signing.

Received an offer from a developer, or an agreement to sign?

We will go over it before you sign. Our firm accompanies apartment owners and owners’ committees in Pinui Binui and TAMA 38 transactions in Israel: choosing a developer, negotiating the agreement, the consideration and the securities, the tax aspects, accompaniment through delivery of the new apartments and their registration, and representation in disputes before the Superintendent of Land Registration and in the courts. In the first conversation we will go over the offer you received and mark what is missing from it. We represent clients throughout Israel and abroad, mostly by phone and video.

For an initial conversation: +972-2-509-0170
Adv. Mike Gabriel, Partner, Head of Real Estate at Bodenheim Gabriel & Co., leads the firm’s real estate work: sale and purchase transactions, transactions within the family, real estate taxation, buyers of apartments from developers, co-ownership and partition, inheritance and registration. Our real estate practice. Bodenheim Gabriel & Co., 214 Jaffa Street, Jerusalem.

This article is intended for general information only and does not constitute legal advice or a substitute for it. Urban renewal legislation is updated frequently, and the dates and conditions are correct as of the date of writing. Last updated: November 2026.

Main sources

  • Land Law (Strengthening of Condominiums Against Earthquakes), 5768-2008, Sections 5, 5A, 5B, 5C, 5D, 5E, 6A and 7
  • Pinui Binui (Encouragement of Pinui Binui Projects) Law, 5766-2006, Sections 1, 2, 2A and 3
  • Real Estate Taxation (Capital Gains and Acquisition) Law, 5723-1963, Chapter Five 4 and Chapter Five 5
  • CA 3511/13 Schwarzberger v. Marin (Supreme Court, July 24, 2014)
  • LCA 1002/14 Shomroni v. Kaufman (Supreme Court, July 9, 2014)
  • CA 3301/23 Midili v. Ibuy Binuy Project, 63 HaNevi’im St., Bat Yam Ltd. (Supreme Court, October 7, 2026)
  • Civil Case (Tel Aviv District Court) 25510-11-24 Cohen v. Hazami (October 29, 2026)