By Adv. Mike Gabriel, Partner, Head of Real Estate | Published: November 2026
The Sale Law bank guarantee ensures that you will not be left with no apartment and no money. It does not ensure that the developer will keep to the timetable. For late delivery, Israeli law gives monthly compensation, not the right to get your money back from the bank. The position changes when the delay turns into a crisis: the developer collapses, a receiver is appointed, and delivery is postponed by years. In August 2026 the Tel Aviv District Court allowed buyers in that situation to cancel the contract and call the guarantees, but the Supreme Court has not yet decided the question, and in a 2025 decision it pointed to the difficulties involved. Anyone considering leaving a transaction because of a delay needs to know which of three situations he or she is in.
Our firm accompanies buyers of apartments from developers from the contract stage through delivery and registration, and represents them when a project is delayed or runs into difficulties: demanding the compensation for the delay, reviewing the guarantees, handling the contacts with the developer, the financing bank and the receiver, and proceedings in the courts. The question that comes up in such projects is always the same: “I am holding a guarantee, so why can I not simply get the money?”
A developer may not receive from a buyer more than seven percent of the price of the apartment without giving the buyer one of the securities the Law lists, and in most projects that is a bank guarantee or an insurance policy. The guarantee secures the refund of the money paid on account of the price, but only when one of the events the Law sets out occurs: the seller cannot transfer the apartment because of an attachment or an insolvency order, or an absolute impediment to delivering possession has arisen.
The Supreme Court has read this list narrowly. In the Ovadia judgment it held: “As long as it can still be called an ‘apartment,’ and it can be transferred, the guarantee cannot be called.” The guarantee is there to secure delivery of the apartment or the return of the money, and not performance of the contract to the letter. In another judgment the Supreme Court added that a Sale Law guarantee is not an ordinary autonomous bank guarantee, and cannot be called on first demand (CA 1062/09). The guarantor checks whether one of the conditions for calling it, in the Law and in the guarantee document, has been met.
The practical meaning: a delay, even an infuriating delay of a year, is not one of the events on the list. The apartment is still being built, and it “can” still “be transferred.” We wrote about the difference between this guarantee and an ordinary bank guarantee in the article on the autonomous bank guarantee.
Delay has a remedy of its own. If the apartment was not placed at your disposal by the end of one month after the date set in the contract, you are entitled to monthly compensation without proving damage: an amount equal to the rent of an apartment similar in size and location until the end of the fourth month, the same amount multiplied by 1.25 from the fifth month until the end of the tenth month, and multiplied by 1.5 from the eleventh month onward. If the contract sets higher compensation, the higher amount is due. The compensation is paid at the end of each month, not at the end of the road.
The developer has only two defenses: that the delay was caused by an act or omission of the buyer alone, or that it results from circumstances that meet the conditions of frustration in the Contracts (Remedies for Breach of Contract) Law. These provisions protect the buyer, and a contract cannot derogate from them.
Late delivery of an apartment by a developer
Three situations, three answers
The guarantee comes into play only when the apartment itself is at risk, not when it is delayed.
A delay, and the developer is active
Section 5A of the Sale (Apartments) Law; Section 2(1) of the Assurance of Investments Law
A delay of years and a receiver who completes
Insolvency File 46530-04-26; CA 13991-08-25
The apartment cannot be received
Sections 2(1), 3A1 and 3C2 of the Assurance of Investments Law
The difficulties in the construction sector in recent years have produced a situation the Law does not expressly answer: the developer collapses, the financing party appoints a receiver, and the receiver does not return money but keeps building. The apartment will be delivered in the end, but two or three years after the date. May a buyer who cannot wait leave and receive his or her money from the guarantee?
July 2025. The Tel Aviv District Court held, in a project whose apartments were due to be delivered in 2021, that every buyer is entitled to choose: to cancel and call the guarantee, or to wait for completion. The financing parties appealed. The Supreme Court justice who heard the application to stay the judgment stayed it, and wrote, “without setting anything in stone,” that the question whether a delay of years together with the appointment of a receiver gives rise to a ground for calling the guarantee is “a question worthy of examination,” and that there is a difficulty in calling guarantees for only some of the buyers, and in requiring the financing parties to complete the project and at the same time pay out guarantees (CA 13991-08-25, decision of September 14, 2025). The appeal was never decided: the District Court judgment was later set aside, and the appeal was struck out in December 2025.
August 2026. The same District Court returned to the question in a TAMA 38 project. A receiver was appointed in May 2026, and under his plan the apartments will be delivered in November 2027. Two families asked to leave. The court allowed them to cancel the contracts and call the guarantees, and held that the other buyers may stay: “When the development company they contracted with collapses, and the financing parties step in and appoint a receiver on their behalf, I believe that this is a crisis point at which a buyer who so wishes may be allowed to call the Sale Law guarantee he holds and leave the project” (Insolvency File 46530-04-26, August 23, 2026). This is a decision of a District Court, which presents itself as an expansive approach set against the older case law. It is not binding precedent.
October 2026. The Supreme Court gave a comprehensive judgment on the position of buyers when the financing party completes a collapsed project. It repeated that the purpose of the guarantee is focused, and that the choice between paying out the guarantees and completing construction is made, as a rule, according to the business considerations of the financing party and not according to the buyers’ preferences. But it also held that the choice cannot be selective: whoever completes the project and collects the full price from the buyers may not cancel their right to compensation for the delay. Compensation for the period from the start of the proceeding to enforce the charges onward ranks ahead of the financing party’s rights, and compensation for the period before that is claimed as a past debt (CA 3301/23, October 7, 2026). As for the question whether a buyer may demand that the guarantee be called when the financing party has chosen to complete, the Supreme Court noted that it did not arise in that case, and it remains open.
| The situation | What is available to you | The guarantee |
|---|---|---|
| A delay of months, the developer keeps building | Monthly compensation under Section 5A, from the end of one month after the contractual date | Cannot be called |
| A prolonged delay amounting to a fundamental breach, the developer is active | Cancellation of the contract and a claim against the developer for restitution and damages | Cancellation in itself is not a ground for calling it |
| Agreed cancellation with the developer | Restitution as agreed | In one case the Supreme Court recognized that the guarantee also secures such restitution (CA 911/10). Depends on the circumstances and the wording |
| A receiver was appointed and is completing construction with a long delay | Compensation for the delay, part of which ranks ahead of the financing party’s rights; an application to the court to allow an exit | Open question. The Tel Aviv District Court allowed it, the Supreme Court has not decided |
| The project has stopped and the apartment cannot be transferred | A written demand to the guarantor to pay under the guarantee | Can be called |
A buyer who lives abroad can deal with a delayed project in Israel without flying in. Our office can send the demands, review the guarantees and appear in the proceedings for you, and where your signature is needed in Israel, we can act under a power of attorney signed before an Israeli consul, or before a local notary with an apostille.
No. A delay is not one of the events that entitle you to call the guarantee, and the apartment can still be transferred. What you are owed is monthly compensation from the developer, from the end of one month after the contractual date, with no need to prove damage.
Not necessarily. The Law provides that cancellation of the sale contract is not in itself an “absolute impediment” to delivering the apartment. After a lawful cancellation, the claim for restitution is directed at the developer. The guarantee will be available to you only if one of the conditions for calling it, in the Law and in the guarantee document, is met.
This is the disputed question. In August 2026 the Tel Aviv District Court allowed buyers in this situation to cancel and call the guarantees. The Supreme Court has not yet decided, and in a 2025 decision it pointed to the difficulties in calling guarantees for only some buyers. The answer depends on the circumstances of the project, the length of the delay and the position of the court supervising the receivership.
The Supreme Court held in October 2026 that a financing party that chooses to complete the project and collect the full price may not cancel the buyers’ right to compensation for the delay. Compensation for the period from the start of the enforcement proceeding ranks ahead of its rights. Compensation for the period before that is claimed in a proof of debt, together with the developer’s other debts.
The money you paid on account of the price of the apartment, linked according to the linkage method in the contract. The VAT component is not covered by the guarantee itself, and it is refunded from a government fund set up for that purpose, through the guarantor.
The statutory compensation is due from the end of one month after the date set in the contract, and it cannot be contracted out of to the buyer’s detriment. A clause in the contract that allows the developer to postpone the date is examined under the provisions of the Law and the circumstances of the postponement.
We will first check what your guarantee actually covers. Our firm represents buyers of apartments from developers in Israel in projects that are delayed and projects that have run into difficulties: demanding compensation for the delay, reviewing the guarantees and vouchers, cancellation of the contract and restitution, representation before the financing bank, the receiver and the trustee, and applications to the court. In the first conversation we will go over the contract, the guarantees and the state of the project, and tell you which routes are open. We represent clients throughout Israel and abroad, mostly by phone and video.
For an initial conversation: +972-2-509-0170This article is intended for general information only and does not constitute legal advice or a substitute for it. The case law on calling a Sale Law guarantee because of delay is still developing, and it is correct as of the date of writing. Last updated: November 2026.